93 Center Ave.  Westwood, NJ 07675 - 100% Volunteer
 

 

CHEERS FOR NEW WESTWOOD FIREHOUSE:

10-YEAR PROJECT'S GRAND OPENING SET


Bergen Record
By DEENA YELLIN, STAFF WRITER
Date: 07-26-2005, Tuesday

WESTWOOD - Uncork the champagne.

It has taken more than 10 years, three contractors and $3.5 million, but despite the myriad debacles, the new Westwood firehouse is finally finished.

The red brick, three-story building will hold its grand opening Sunday from 1 to 3 p.m.

"We are all thrilled to be returning to our home," said Westwood Fire Chief James Cole.

Westwood Fire Department members will march from the DPW building on Harrington Avenue, where they have been temporarily housed, to their new home on Center Avenue at around 12:50 p.m.

The firefighters will parade through the street followed by a crew of bagpipe players and the company's fire apparatus. The four chiefs who have served during the department's tenure in the DPW building will park the firetrucks in the four new bays.

Residents are invited to tour the new building during a two-hour open house, in which WFD members will be available to answer questions and offer fire safety tips.

Councilman Peter Grefrath, the council liaison to the building project for seven years, is overjoyed with the results.

"The building is beautiful. It's well-designed and can hold all of the equipment easily. It will also be able to be used as an emergency shelter in case Westwood residents ever have to vacate their homes," Grefrath said.

The building also contains offices, a training room, a kitchen, a state of the art communications center and a generator that can independently sustain power for the building.

It wasn't an easy process. There were many obstacles over the years. First, borough officials and residents debated what kind of building should be built and at what cost.

Once construction began, a storm ripped through town and blew down the walls. Then the contractor went bankrupt and the architectural firm disbanded.

When new experts examined the plans, they found defects in the building. A new design and rising construction costs increased the project from $1.3 million to more than $3 million.

Then borough officials complained that the contractor was taking too long to finish the job and hired a new contractor after the second contractor went into default for not paying subcontractors.

The building finally received a certificate of occupancy last week, and the department has slowly been moving in.

"It has been long-anticipated, and we're glad to finally be able to move in and have a place where we can call home," said a beaming Darren Blankenbush, a fire official. "It sure beats the rental trailer I've been working out of for eight years."

Westwood's first firefighting unit, Continental Hook and Ladder Company No. 1, was established on Feb. 17, 1884. The first firehouse was built in September 1894 on land where the current firehouse stands.

The original firehouse was expanded in 1910 to include a second bay for a new firetruck. In 1928, the original firehouse was demolished and the borough constructed a municipal building that housed the fire department.

The building eventually became dilapidated and outdated and could not accommodate today's fire equipment. So borough officials pursued the idea of constructing a new building. The municipal hall-firehouse was razed in 1997 to make way for the new headquarters.

But not everyone is thrilled with the project's completion.

"As a resident frustrated with rising taxes, I wish the oversight had been more tenacious toward containing costs during the past decade this project has lived," said Mayor Thomas Wanner. "The way it was, the net cost is approximately $3 million - no small change in any taxpayer's pocket."

Borough Attorney Russell Huntington denied that the catastrophes surrounding the firehouse project were a result of borough mismanagement, as some have charged.

"This is more of a reflection of the system that the Legislature has stuck the towns with than the local officials who have to try to operate within that system," he said.

He pointed out that state laws limit municipality projects, such as the requirement to choose the lowest bidder and to limit what can be set aside for cost overruns.

***

Fast facts

* The new red brick firehouse at Center and Jefferson avenues is three stories tall and includes a mezzanine.

* The building has 14,552 square feet.

* It has four truck bays; several offices, including a fire prevention bureau office; a social hall; a kitchen, and a state-of-the-art communications room.

* The borough spent $4.5 million overall but was refunded $1 million from its insurance company for delays caused by the former engineer, architect and contractor.

* The borough still has outstanding claims against Poppe General Contractors Inc., and hopes to recoup more costs.

 

2004 - 2008 - Westwood Volunteer Fire Department - all rights reserved - all images and text protected by copyright